From estimate to working plan.

Engineering decisions for monolithic concrete works in Czech and Slovak markets. Approximate calculation — but very accurate. Built by a working construction estimator.

Book a 20-min demo
Web-based — no installation Czech construction norms (ČSN, OTSKP, TKP) 200 credits free at signup
17 904 items in the OTSKP database

Who StavAgent is for

Cost estimator (rozpočtář)

Classify tender items into custom groups for supplier RFQs and internal departments. AI suggests codes from the description — always with probability, never with 100% certainty, always to be reviewed.

Site preparation (přípravář)

Pour stages, resources, crew composition, schedule. Formwork, reinforcement, concrete works — at single-element or whole-object scope. TOV resource breakdown.

Construction firm / general contractor

Overview across all objects and budgets. Tenders split into groups, ready for supplier RFQs. Built-in calculators for concrete pump (multi-supplier formulas), delivery, and crane.

Bridges and infrastructure

Bridge elements (piers, abutments, decks, cornices), prestressing, pour stages. Czech norms ČSN EN 13670, ŘSD specifications, OTSKP classification — proof of domain authenticity.

What StavAgent does

Three connected tools for the entire estimator workflow.

Klasifikátor — construction works classifier

AI classification of tender items. Upload bill of quantities (xlsx), paste one description, or upload documents (PDF, DWG) — the system finds OTSKP candidates and suggests codes with probability. Never with 100% certainty — always for user review.

  • 3 input methods: bill of quantities (xlsx), free text, documents (PDF, DWG)
  • 2 modes: quick (~2–3 min) or extended with multi-role validation and ČSN check (~5–10 min)
  • Confidence on every suggestion — AI never 100%, always to be approved by user

Registr — tender workshop

Split a tender into your own groups for supplier RFQs and internal departments. For each item, a TOV breakdown: people, machinery, materials. Built-in calculators for concrete pump, delivery, and crane.

  • Classify items into custom groups for supplier RFQs and departments
  • TOV (technical-organizational breakdown) — every work item split into people, machinery, materials
  • Built-in calculators: concrete pump (multi-supplier formulas), concrete delivery, crane

Kalkulátor — concrete works calculator

Calculate concrete, formwork, reinforcement, pour stages and resources. Two modes: single-element detail or whole-object plan — both with schedule and Kč/m³ cost.

  • Single-element detail — 7 deterministic engines (formwork, reinforcement, pour decision, DIN 18218 lateral pressure, Saul maturity, RCPSP scheduler + PERT, pumping)
  • Whole-object plan — table with pour stages, resources, Kč/m³
  • 25 formwork systems (DOKA, PERI, ULMA, NOE, traditional), 24 element types, ČSN EN 13670 + TKP 18 + DIN 18218 compliant
Coming soon — early access list open

Document Analysis

Technical reports (TZ), structural design, geology, drawings. Cross-document checks: geology → structural → tender. AI extracts key parameters and compares with other documents in the project.

  • 12+ types of construction documentation (D.1.2 structural, D.1.3 fire safety, C geology…)
  • Cross-document check: geology → structural → tender
  • Determinism first: regex extraction (confidence 1.0), AI only as a probability supplement
Join early access

How it works

1

1. Klasifikátor

Standalone lookup tool. Paste a bill of quantities (xlsx), a single item, or upload a document (PDF, DWG) — AI suggests OTSKP codes with probability. Always for user review, never with 100% certainty. Output: Excel, CSV.

2

2. Registr

Tender workshop. Import your bill of quantities (xlsx), split into custom groups for supplier RFQs and departments. TOV — every work item broken down into people, machinery, materials. Built-in calculators for concrete pump, delivery, and crane.

3

3. Kalkulátor

Single-element detail and whole-object plan — concrete, formwork, reinforcement, pour stages, schedule. Resource map (crews, curing time, formwork strike time) available as export for import into TOV in Registr.

4

4. Export TOV/DOV

Excel from each module for suppliers and departments. Hyperlinks back to source file preserved. Price and schedule ready for RFQ.

Why deterministic calculations, not just AI

Regex parsing (conf. 1.0)

Concrete grades C25/30, ČSN norms, dimensions, thicknesses — exact extraction without AI.

OTSKP database (conf. 1.0)

17 904 items with verified codes, descriptions and units.

AI only as supplement (conf. 0.6–0.85)

Gemini Flash + Claude only when regex and DB find no match. Never 100% — always to be reviewed.

Every result carries a confidence score. You always know what is a deterministic calculation (100%) and what is an AI suggestion (60–85%). No hidden hallucinations — just transparent calculation with an audit trail.

Real examples

Two real cases: a public ŘSD tender and an anonymized project from portfolio.

Public ŘSD tender

SO-202 D6 Karlovy Vary–Olšová Vrata — bridge on road I/6

Source: TZ PDPS VD-ZDS, VIAPONT s.r.o.
Input
  • Bridge on D6 motorway, km 0.900 (2 bridges LM + PM)
  • 6 spans, lengths 15 + 4×20 + 15 m
  • Double-T prestressed deck, width 10.85 m
  • Concrete C35/45 XF2, curing class 4
  • 12 cables × 13 strands Y1860, one-sided stressing
  • Piles Ø 900 mm, depths 7.5–16 m
What StavAgent computed
Deck volume:       ~ 350 m³
Formwork area:     ~ 1 210 m²
Falsework:         Top 50 (girder system)
Props:             Staxo 40 (h < 8 m)
Curing:            9 d (XF2 class 4, 15–25 °C)
Prestress:         7 d wait + 2 d stressing + 2 d grouting
Piles:             122 ks, C30/37 XA2
TOV: concreters, carpenters (falsework + props), reinforcement crew, stressing crew · concrete pump, crane · concrete, reinforcement, cables, grouting mix
Export TOV/DOV → Excel for RFQs and departments30 minutes instead of half a day in Excel
Real project (anonymized)

Retaining wall — industrial site, 156 m length

Real geometry · client identification withheld
Input
  • Linear retaining wall along a manipulation area
  • Length 156.4 m
  • Cross-section (T): stem 1 450 × 250 mm + footing 800 × 300 mm
  • Visible height 1.75 m + footing 0.3 m
  • Concrete C30/37 XF4
What StavAgent computed
Volume:           94.231 m³
Formwork area:    547.4 m²
Reinforcement:    5.654 t (D12)
Pour stages:      8 segments × 19.5 m
Formwork system:  Framax Xlife (frame)
Crew:             4 workers + 2 pumps
Schedule:         12 working days
TOV: concreter × 12 d, carpenter (formwork install/strike), reinforcement crew · concrete pump, crane · concrete 94 m³, reinforcement 5.7 t
Export TOV/DOV → Excel for RFQs and departments30 minutes instead of half a day in Excel

This calculator provides an approximate estimate for budget preparation with typical accuracy ±10–15%. The final detailed design, structural calculation and exact component specification are always performed by the formwork supplier (DOKA / PERI / ULMA / others) based on specific project documentation. For the tender phase and preliminary calculation, this accuracy is sufficient.

What StavAgent does NOT do

Calculator boundaries. What the supplier (DOKA / PERI / ULMA) owns, and what we own.

Not a final engineering software

For detailed structural design, load calculations and approval documentation → DOKA / PERI / ULMA design teams.

Not a competitor to DOKA Software / PERI EngineeringPad

It is a complementary tool — it prepares the materials for discussion with the engineering team, it does not replace them.

Not an inventory tool down to the last screw

The calculator computes main systems and consumable percentages; specific screws, anchors, custom adapters are handled by the supplier.

Not a guarantee of an exact price

The final price comes from the supplier’s structural design + current price list + project documentation. The calculator provides an approximate estimate for the tender phase.

Our value = speed + technological correctness + vendor-neutrality in the pre-tender estimation phase.

Engineering under the hood

17 904
OTSKP items
24
element types
25
formwork systems
12+
documentation types
Norms: ČSN EN 13670, DIN 18218 (formwork lateral pressure), TKP 18 (concrete works curing), Saul maturity model
Deterministic core: regex + database (confidence 1.0)
AI layer: Gemini Flash + Claude Sonnet (confidence 0.6–0.85, always to be reviewed)
Infrastructure: Google Cloud (EU, Frankfurt) + Vercel

Pricing

Open beta. 200 credits free at signup.

Sign up: 200 credits FREE

Just register and you can start immediately. No credit card, no commitments.

Open beta — paid plans launch in Q3 2026 via Lemon Squeezy (Merchant of Record).

Frequently asked questions

Do I need to install anything?
Which file formats do you support?
How accurate are the classification results?
How accurate is Kalkulátor?
Does it work for bridges and infrastructure?
Does StavAgent work with catalogs?
What is TOV?
Can I choose the AI model?
Can I import the output back into my existing application?
Is my data safe?
How much does it cost?
When will you start charging?

Save hours of work on construction documentation.

Try StavAgent free — 200 credits at signup.

Book a 20-min demo

or email: info@stavagent.cz